Below are the "shovel-ready" projects for which this city has requested federal stimulus funding. You can click on a project to read (and add to) its description. You can also discuss the project and vote on whether you believe it is critical or not.
The total cost of all the projects submitted by Cocoa Beach is $42,688,000
Description / # of Jobs / Cost / Program Type / Vote Ratio
Ocean Beach Blvd. use native plants/energy-efficient lighting. Intended to aid in controlling runoff to Indian River lagoon. (design phase complete)
50 $2,000,000
Streets/Roads -4
http://www.stimuluswatch.org/project/view/3538
20 $1,000,000
Streets/Roads -6
http://www.stimuluswatch.org/project/view/3536
10 $400,000
Streets/Roads 0
Asphalt rejuvination - City-wide project to extend life of existing paving
10 $350,000
Streets/Roads -3
SR 520 Landscaping & Irrigation - Intended to aid in controlling runoff to Indian River lagoon
10 $250,000
Streets/Roads -4
Completion of Sidewalk /Bike Path Master Plan
10 $150,000
Streets/Roads -7
Improvements to six (6) process systems: (1) Influent Handling Facilities (2) Biological Treatment Units (3) Clarifiers (4) Filters (5) Chlorine contact (6) Residuals Handling (Study & preliminary costing done)
50 $10,938,000
Water 0
Sewer System Rehabilitation - Rehabilitation of systems serving Lift Stations #4, #6 & #7 (Specific upgrades required are identified)
20 $3,000,000
Water 1
Engineering evaluation of ASR site at PAFB. Construct 500,000 GPD irrigation system.
20 $750,000
Water -7
Infiltration & Inflow Assessment - Comprehensive survey of system to prioritize work required
5 $500,000
Water 0
Lift Station # 4 Conversion - Major upgrade to "wet pit" status
20 $400,000
Water 0
Rebuild and/or replace six (6) high service pumps (Equipment identified & replacements specified)
10 $250,000
Water -1
Administration facility solar powered/LEED certified energy-efficient lighting (property acquired/needs assessment study done) )(must receive funding early 2009 to complete by end of 2010)
50 $8,000,000
CDBG - 7
Vehicle storage building - solar powered/LEED certified Intended to extend vehicle life by corrosion reduction
10 $150,000
CDBG -2
Equipment Storage building - solar powered/LEED certified Intended to extend vehicle life by corrosion reduction
5 $50,000
CDBG 0
Install solar power grid. Provide power to some City facilities & sell remainder to grid. (Installation areas identified & available)
10 $500,000
Energy 2
Public Safety (combined police/fire) facility,solar powered/LEED certified energy-efficient lighting (property acquired/needs assessment done)(must receive funding early 2009 to complete by end of 2010)
100 $12,000,000
Public Safety -3
Construct Fire Station # 2 solar powered/LEED certified energy-efficient lighting (property acquired/needs assessment done))(must receive funding early 2009 to complete by end of 2010)
70 $2,000,000
Public Safety -1